Introducing the footsteps of Ulsan GPS.
-
2010
-
December
- Applied the 5th Electricity Supply Basic Plan (coal power generation, Dangjin)
-
2014
-
December
- Acquisition of Dangjin Coal Power Generation (SK Gas)
-
2018
-
December
- Applied the 8th Electricity Supply Basic Plan fuel conversion (Coal → Gas)
-
2019
-
June
- Acquired permission to change Ulsan GPS Power Plant (LNG·LPG Combined Power Generation) development project
-
August
- Ulsan GPS business site relocation (Dangjin → Ulsan)
-
2021
-
July
- Completed environmental impact assessment consultation
-
December
- Received approval of power source development implementation plan
-
2022
-
March
- Received approval of construction plan
- Began power plant construction
-
August
- Acquired integrated environment license
-
2024
-
January
- Gas turbine initial ignition
-
December
- Commence commercial operation