Introducing the footsteps of Ulsan GPS.
  • 2010

    1. December

      • Applied the 5th Electricity Supply Basic Plan (coal power generation, Dangjin)
  • 2014

    1. December

      • Acquisition of Dangjin Coal Power Generation (SK Gas)
  • 2018

    1. December

      • Applied the 8th Electricity Supply Basic Plan fuel conversion (Coal → Gas)
  • 2019

    1. June

      • Acquired permission to change Ulsan GPS Power Plant (LNG·LPG Combined Power Generation) development project
    2. August

      • Ulsan GPS business site relocation (Dangjin → Ulsan)
  • 2021

    1. July

      • Completed environmental impact assessment consultation
    2. December

      • Received approval of power source development implementation plan
  • 2022

    1. March

      • Received approval of construction plan
      • Began power plant construction
    2. August

      • Acquired integrated environment license
  • 2024

    1. January

      • Gas turbine initial ignition
    2. December

      • Commence commercial operation